Construction In Progress

Civil Engineering Corporation of Hakik 4 Redevelopment

페이지 정보

작성자 BAN SEUK CONSTRUCTION CO., LTD 작성일2022-08-11

본문

  • Project title: Civil Engineering Corporation of Hakik 4 Redevelopment
  • Construction Period: August 5, 2022 to May 30, 2025
  • Main Contractor: HANWHA ENGINEERING & CONSTRUCTION CORP.
  • Client: Hakik District 4 Housing Redevelopment and Maintenance Project Association
  • Overview of Construction: Earthworks and temporary facility construction work, CIP, grouting, auxiliary civil works, etc.
Construction Information

[Work scope]  

1) Earthwork : Excavation 136,000㎥, Refilling 4,500㎥, Disposal 136,000㎥

2) Temporary facility construction woek : CIP 16,000m / ASG grouting 11,986m / Post-Pile 1,200m / Wale 2,680m / E/A 6,634m / Raker Pile

3) Auxiliary civil works. etc.